GM3WOJ ZL1CT Lattice tower information pages
August 2008 - Installation of 2 x BP80 Versatowers at the GM0NAI / GM7R contest station, located on the Black Isle (IO77uo)
22nd August 2008 - preparing the bolt templates and shuttering
carefully measured shuttering and bolt template - all strongly screwed
together
close-up of bolt mounting - note the nut and washer below, to ensure bolts
are held vertically
small wooden packing pieces ensure correct height of bolt ends above surface
of concrete
Jim GM0NAI checking the position of the tower earth strap
one of the Versatower guy stakes
Jim hammering one of the guy stakes in
oops - how to correct a wrongly-aligned tower hole !
25th August 2008 - pouring the concrete for the 2 bases + 6 guy stakes (8 cubic metres of concrete = 19.2 tonnes total)
Andy GM0UDL (red overalls) supervising the pouring of the concrete into the
dump truck
Jim using the vibrating poker to level the concrete
Andy GM0UDL and Jim GM0NAI/GM7R - job finished !
one of the 6 guy stakes after concreting
one of the 2 tower bases after concreting
28th September 2008 - installing the tower bases and first sections
Martin 2M0ALS arriving with the GM7R towers on his trailer - 2 x BP80, 1 x BP60,
3 x 36' mini-towers, 17 x 12' fixed tower sections ( = 204' total )
L to R - Jim, Sahara (Pippa's nephew visiting from S Africa), Martin
the tower baseplate and post after lowering onto the bolts (Jim tidying up the
grouting)
preparing the second tower - securing the luffing wire and removing the old
wires from the sections
something vertical at last ! Tower #1
5th October 2008 - wiring up the tower sections
K2550 winch drum with uprated 8mm diameter luffing wire
the uprated 8mm luffing wire runs easily through all the pulleys
Jim raising tower #1 to full height for the first time. Early winter snow on
Ben Wyvis in the distance
tower #2 at full height for the first time
More photos of this great project soon ......